Solar paired system provides demand charge management to reduce peaks for manufacturing facility
- Tracy Fosterling
- Acumen EMS, Demand Charge Management
Project Summary
Location
Dickson, Tennessee
ESS Provider
Chint Power Systems
System size
180kW/390kWh across 4 sites
Deployment Date
May 2020
Facility type
Manufacturing facility
EMS Application
Demand Charge Management,
The Challenge
The office supply manufacturer with a 400,000+ square foot manufacturing facility and warehouse wanted to pair energy storage with their roof-mounted solar PV system to shave peak demand, which results in high demand charges and electric bills. Energy Toolbase’s Acumen EMS™ integrated with a Chint Power Systems (CPS) energy storage system was deployed to optimally shave peak and reduce the customer’s demand charges.